Runway 3 Project for HK Airport

After studying the HK hotels more – we learned about a new Runway 3 (I would call it a Terminal 3) that is set to open in 2022, 2024.

Here’s the public timeline, which can be found on the official Project website

2011
Public consultation of HKIA Master Plan 2030

2014
Approval of the Environmental Impact Assessment report and issue of the Environmental Permit

2016
Commencement of the construction of the three-runway system

2018
Completion of the installation of two new 5.2-kilometre aviation fuel pipelines using the environmentally-friendly horizontal directional drilling technique

2020
Completion of reclamation

2022
Opening of the new North Runway

2024
Completion of the three-runway system